Thompson Square

On the opening of the new Windsor Bridge

I was privileged to have a sneak peak of the new bridge before it opened with Robyn Preston MP

The new Windsor bridge opened to traffic this weekend. This is a major milestone, and the project has dominated local politics for a decade.

After so much Ill-feeling and unnecessary delay, I think this is a project the whole community should be proud of, and I say this as a local representative who felt very much caught in the middle by those passionately advocating for and against.

I didn’t entirely agree with those who thought of this project as a rape of Windsor’s heritage. But I did agree that building a replacement bridge in the same location condemned a very historic square to another century of heavy traffic, when it offered a wonderful opportunity to build a bypass. I said then and still say that this was a missed opportunity.

"Slated for demolition"... except it never was.

I also disagreed strongly with those who put out misinformation — saying for example that heritage buildings around Thompson square were “scheduled for demolition” when they never were, and the protesters knew that. They also said that historic brick barrel drains that had been covered up over a century would be destroyed, when in fact the project afforded the chance to do some unique archeology and then cover them back up, just like they have been all this time. We now have a documentary record and a host of artefacts we never would have otherwise had. Piers for the new bridge were moved so that they didn’t disturb the drains. 

Some wonderful archeology was uncovered by the project, which never would have been investigated otherwise.

Nor did I see overwhelming merit in retaining a narrow, inadequate bridge whose visible structure was an ugly concrete deck added in 1924. The oldest part of the bridge, best able to be described as having heritage value, were the iron pillars driven into the river bedrock in 1874 — some of which will be retained in the construction of a viewing platform (which the protesters opposed!) 
These things inflamed passions and tested friendships needlessly.

Of course, any protest started by people who care deeply about heritage or local amenity also attract carpetbaggers — people who care less about the issue, but who beadily seized an opportunity to create political friction for their own ends.

For years, I saw protests in Thompson Square with unsavoury types loitering around the edges — leather clad union thugs, federal politicians who had nothing to do with the project, Greens activists, even the late Jack Mundey, former BLF tsar and Communist Party candidate (but otherwise the saviour of The Rocks — see, people aren’t all bad).

It became a circus. At the last election, at least three people gained election to Hawkesbury Council on the back of this tide of protest, only to spend the last four years sticking their heads in the sand, opposing reasonable collaboration between Council and the RMS, and almost guaranteeing that the community input they sought election on would rarely reach the right ears. It’s been very frustrating. 
I think many people who genuinely care about heritage have been used.

It’s worth noting that today's opening of the new bridge isn’t the end of the project. I’m hopeful that the completed landscaping will reunite the sundered halves of Thompson Square caused by the cutting dug in 1934, greatly expanding the useful space to the public, and underlining that Thompson Square has been a changing and evolving space since the beginning.

The opening of the old bridge, 4th November, 1874. This bridge shares only certain elements with the present structure. The whole top deck was replaced in 1920.

I’m confident that once everyone sees the completed project, people will reconsider whether all the noise and hand-wringing were worth it.

Hawkesbury, enjoy your new bridge. Maybe your great-great grandchildren will fight to preserve it as a piece of the area’s heritage in 2166, the year in which it will be as old as the current bridge retired at. 

This video, courtesy of Robyn Preston MP - Member for Hawkesbury is a fascinating record of the bridge's construction.


Finding common ground on Windsor Bridge

thompson-square-protest

There is no more controversial issue before the new council than the project to replace Windsor Bridge. It is an issue that has tested friendships, inflamed passions within the community, and created a protest movement that uses every trick in its playbook to prevent the project proceeding.

There will be much more to say on the matter of the bridge, and of the larger issues it augurs relating to the future of our district. I hold particular views on the subject, but this post makes no argument. Yet.

And why? Because there are seven new councillors on council, myself included. I feel that the first step, the step that must occur before a substantive debate about the bridge occurs, must be for the new council to be properly briefed by the relevant departments.

So, at the council meeting on Tuesday, I moved my first Notice Of Motion which called for a briefing to be given to us on the project. I asked that the briefing be held either in Thompson Square, or in Chambers (or both), and that relevant RMS, ministry and council staff be present. Councillor Richards and Councillor Reynolds had moved similar motions of a more limited scope, relating generally to support for an extra river crossing, and relating to an overall traffic strategy respectively. I am pleased that both of those councillors acknowledged that my own motion encompassed their concerns, and with their permission and certain amendments, they withdrew their motions and the following was put:

"That Council:

Support an additional crossing of the Hawkesbury River.

  1. A Councillor Briefing, incorporating presentations from relevant RMS and Council staff be held to provide details on the current status of the Windsor Bridge project.
  2. This Briefing should address project status, heritage, traffic performance, design and aesthetic issues (including open space) and maintenance responsibilities.
  3. A further Briefing be held for RMS and Transport for NSW officers to outline options and planning for future river crossings including commentary on the impacts of proceeding with the current Windsor Bridge replacement.
  4. That Briefing canvas the various options to give substantive effect to achieving the actions and funding of studies and investigations."

My background to the motion, furnished to assist my colleagues to understand why this was important, stated:

"The state of the Windsor Bridge replacement project is the most contentious issue before the new Council. The expectation of some is that Council should quickly resolve to reverse its former support for Option 1 and now formally oppose the project.

With seven new Councillors in the new term, there is clear merit in receiving a briefing on this issue before such a resolution comes before the Council, especially when it seems obvious there is sincere disagreement on some matters of fact.

To assist the General Manager identify which public officials should be invited to best achieve the briefing’s purpose, and to permit those officials to be adequately prepared, it is proposed the matters to be discussed could include (but not be limited to):

  1. The current state of the bridge replacement project (true cost and timeframe).
  2. How the project is identifying and conserving the heritage of Thompson square.
  3. The status of nearby heritage items, including number 10 Bridge St, the colonial era drainage works, the School of Arts steps, and the remnants of Greenway’s wharf.
  4. The evidentiary basis for predictions relating to improved traffic flow.
  5. The adequacy of the project to deal with projected traffic flows on a multi-decade horizon.
  6. The proposed aesthetic qualities, form, fabric, scale and position of the new bridge.
  7. How the project will manage the slope between the upper part of Thompson square park and the water.
  8. What ongoing input Council can have in ensuring the renewed precinct will suit the communities’ needs as regards amenity, aesthetic design (stone, ironwork, landscaping etc), tourism, mobility access, parking, historical interpretation and so on – which will be Council’s responsibility to manage after State-managed works are complete.
  9. What the options are for a longer term plan for future river crossings, such as the suggestion that an additional crossing form part of the feasibility investigations for the M9 orbital.
  10. What the cost of Option 8 from the 2011 RTA study would have been, which was for a downstream bridge near Pitt Town, and how it compares to the likely final cost of Option 1.
  11. Whether the time-frame or funding of such a future crossing is in any way affected by the completion or cancellation of the current bridge replacement project."

I am well aware that feelings run strong on this issue, and my expectation is that those councillors who oppose the project should and will ask many pointed questions when the briefing is held. I hope they do! Ultimately, eleven of the councillors voted in favour of my motion, which is pleasing.

The sole vote against the councillors receiving this briefing came from CAWB member, John Ross. I'll repeat that: On the very issue that elected Clr. Ross to Council, my worthy colleague voted against councillors even receiving a briefing, even after I had made it clear that it must be regarded as the first step towards a productive, rather than an angry and sterile, debate.

I will have much more to say on the subject of Windsor Bridge, but I will do so after this briefing has been given.